Project Updates

Projects in the WRA Conveyance System

Project Name Contractor Contract Award Amount Percent Complete
WRA Eastside Interceptor, Phase 27, Segment 1 SM Hentges & Sons $9,566,765.35 98.3%
WRA Eastside Interceptor, Phase 27, Segment 2 SM Hentges & Sons $5,204,285.81 97.0%
WRA Eastside Interceptor, Phase 27, Segment 3 SM Hentges & Sons $8,836,811.51 96.3%
WRA Eastside Interceptor, Phase 27, Segment 4 SJ Louis Construction $5,947,000.00 86.6%
WRA Eastside Interceptor, Phase 27, Segment 4A Synergy Contracting $2,386,324.00 4.2%
WRA Eastside Interceptor, Phase 27, Segment 5 SM Hentges & Sons $13,165,520.00 86.6%
WRA Eastside Interceptor, Phase 27, Segments 6 & 7 SM Hentges & Sons $9,918,773.55 96.3%
WRA Eastside Interceptor, Phase 27, Segment 8 Story Construction $14,195,000.00 73.5%
WRA New Main Outfall, Phase 17, Segment 7 Oscar Renda Contracting $11,136,191.94 99.8%
WRA Fourmile Creek Improvements - North of Euclid RW Excavating Solutions $929,949.00 95.1%
WRA Collection System Televising 2017 Ace Pipe Cleaning $2,071,903.80 97.0%
WRA Beaver Creek Interceptor Sheet Piling Stabilization Peterson Contractors $1,138,082.00 75.0%
WRA West Des Moines Outfall Emergency Sheetpile Replacement Jensen Construction Co. $290,600.00 83.3%
WRA West Des Moines Outfall Sheetpile Repair Herberger Construction  $556,855.00 88.9%
WRA Sewer Lining - Phase 1 Spiniello Companies $7,863,300.00 7.6%

Projects at the WRF

Project Name Contractor Contract Award Amount Percent Complete
WRA Biogas Conditioning & Injection Improvements Shank Constructors $15,036,400.00 96.1%
WRF Grit Removal Improvements Dean Snyder Construction $12,515,000.00 65.4%
WRF Blended Sludge Pump Replacement Dean Snyder Construction $615,020.00 96.6%
WRF Digester HVAC Improvements AJ Allen Mechanical $575,500.00 97.0%